M
mdxix
How do I make MPP adjust the Units, when it levels, so it allows
parallel tasks?
I have two tasks with some shared resources. Both tasks are fixed
duration. One task is a week long and the other is recurring daily
meetings during that same week.
However, when I Level the plan, MPP shifts the tasks so they are in
sequence, rather than it tries to adjust the work hours to allow both
tasks at the same time.
Is there a way to do that?