D
Dave
1. Create generic enterprise resource 'Egg'
2. New project -> build team from enterprise -> add Egg
3. Create 3 tasks 1 day each and assign to Egg
4. Level project -> Tasks are leveled correctly
5. Save Project as EggProject1
6. New Project
7. Create 3 tasks 1 day each and assign to Egg
8. Level project -> Tasks are leveled correctly
9. Save Project as EggProject2
10. Level project -> Tasks are leveled but now occur 3 days later because
Egg is working on EggProject1
Bahh! But I haven't published any assignments yet!
This basically means that only 'Final' projects should go into Project
becuase draft resource assignments are taken into account even when they are
not yet published.
This is really really really REALLY annoying.
Dave
2. New project -> build team from enterprise -> add Egg
3. Create 3 tasks 1 day each and assign to Egg
4. Level project -> Tasks are leveled correctly
5. Save Project as EggProject1
6. New Project
7. Create 3 tasks 1 day each and assign to Egg
8. Level project -> Tasks are leveled correctly
9. Save Project as EggProject2
10. Level project -> Tasks are leveled but now occur 3 days later because
Egg is working on EggProject1
Bahh! But I haven't published any assignments yet!
This basically means that only 'Final' projects should go into Project
becuase draft resource assignments are taken into account even when they are
not yet published.
This is really really really REALLY annoying.
Dave