leveling question

K

KimC

Jim,
I found the dialog box, but sometimes the Clear Leveling button is not
available. Do I have to Save? not Save? what do I need to avoid doing so I
can be sure the leveling can be undone?
 
J

JulieS

Hi KimC,

The clear leveling button is only available in a Task view, not a
Resource View. If you wish to see what tasks have been leveled, apply
the Leveling Gantt view. The Clear leveling button should be available
from that view as well.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
K

KimC

Thank you--that clears up the mystery!
Kim

JulieS said:
Hi KimC,

The clear leveling button is only available in a Task view, not a
Resource View. If you wish to see what tasks have been leveled, apply
the Leveling Gantt view. The Clear leveling button should be available
from that view as well.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
J

JulieS

You're most welcome Kim and thanks for the feedback. Glad to have
helped.

Julie
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top