F
FSinIDuser
I want to force Project to assign a ONLY full day of work to a resource when
leveling for certain tasks. E.g. I assign Resource A to Task X. Task X is a
field job and requires a full day to complete because of travel to/from the
job site. What happens is, Project levels Resource A to work on Task X for
everything BUT a full day (say 3 hrs/day). Essentially, I want Project to do
this: IF assigning Resource A to Task X THEN Resource A MUCT be assigned at
least 8 hrs/day. Anyone know how to make this happen?
leveling for certain tasks. E.g. I assign Resource A to Task X. Task X is a
field job and requires a full day to complete because of travel to/from the
job site. What happens is, Project levels Resource A to work on Task X for
everything BUT a full day (say 3 hrs/day). Essentially, I want Project to do
this: IF assigning Resource A to Task X THEN Resource A MUCT be assigned at
least 8 hrs/day. Anyone know how to make this happen?