levelling question

G

greg tatchell

if a project has tasks that are either partially or fully completed, does
project leave them alone when you re-level?
 
H

Haris Rashid

hi Greg,

The tasks that are comleted are not levellled as there is no point in
rescheduling a completed task. For tasks in progress the actual start date
won't be changed when levelling. However, as long as the Leveling can create
splits in remaining work check box is selected, any remaining work can be
split for leveling.

Kind regards,
 
J

Joe

Greg,

If you don't want that task to be leveled. Set the Priority to 1000. This
will not level this task (or any task where priority is set to 1000).
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top