Tricky
I have a number of consecutive lines of activity with their own seperate
resource allocation (on various potentially overlapping dates) that i need to
add together to understand my maximum resource of those people on a given day.
So I need to know how to add those resources together.
I also need to know how i alter the resource contraint for various dates,
one week the constraint could be 30, the following week 20, and i need to be
able to tell project those specific dates to understand when i have a bust.
Thanks in advance of any help