Linked Tasks

F

flyhing

I have tasks that are not linked to other tasks which when I move causes
other tasks to move. I tried moving a task a day at a time which initially
diddn't change other tasks then suddenly when I reached a certain date other
tasks move along with it. The only link is that the use the same reource. Any
suggestions what may be causing this?
 
J

JulieS

Hi flyhing,

From your description it sounds as though Automatic Leveling is on. When
you move a task with the same resource assigned, Project is automatically
leveling (adding delay to one of the tasks) to resolve the overallocation.

Check Tools > Level Resources and set the leveling calculation to manual.

Hope this helps. Let us know how you get along.

Julie
 