Need to bring milestones from Proj A over to Proj B and then use them in Proj
B to drive tasks there. I have Project 2003. Proj A is prepared by a
different team, but Proj B work depends on their Milestones.
I 'copy cell' from Proj A and 'paste link' into Proj B. Initially, that
seems to work OK. I save project B first then close it. I then close Proj A,
without saving as it is not my project.
Problem is, when I re-open Proj B, I get messages that say things like, LINK
xx cannot be established between Proj A and Proj B.
I did not change anything in my Proj A or Proj B to sever a link. And, I
cannot determine which milestone in Proj B is identified with the Link xx.
Any ideas? Does this linking work in Project 2003? Doesn't seem to.
Thanks
B to drive tasks there. I have Project 2003. Proj A is prepared by a
different team, but Proj B work depends on their Milestones.
I 'copy cell' from Proj A and 'paste link' into Proj B. Initially, that
seems to work OK. I save project B first then close it. I then close Proj A,
without saving as it is not my project.
Problem is, when I re-open Proj B, I get messages that say things like, LINK
xx cannot be established between Proj A and Proj B.
I did not change anything in my Proj A or Proj B to sever a link. And, I
cannot determine which milestone in Proj B is identified with the Link xx.
Any ideas? Does this linking work in Project 2003? Doesn't seem to.
Thanks