Linking Resource pools back to tasks

G

Gilgamesh

Hello,
I'm looking at using a resource pool with schedules inserted into a
master schedule. But I'm also looking at doing some offline assignment
value changes in Excel and import this back in.

On a single schedule this is easy as I just link it to the UniqueID. But
when I use schedules inserted into other schedules the UniqueIDs all change
but Project is able to keep the assignments sorted out. Can someone tell me
what mechanism is used by MS Project in linking assignments from inserted
sub-schedules to the common resource pool. If I know this I can probably
figure out a means to do what I'm after. Alternatively someone may have a
workaround they are willing to post.

Thanks
 
J

Jan De Messemaeker

Hi,

Import the assignments into the project they belong to (with the pool
closed) instead of into the pool.
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top