Craig --
You cannot. One alternative is to break the split task into two separate
tasks, and link the dependent task to the second of the pair.
Alternatively, you could also use negative Lag (Lead time) on the task
dependency to overlap the dependent task with the split task. Just a couple
of ideas. Hope this helps.