Linking tasks between projects?

R

RoseC

When linking tasks beween projects it appears that the links are between
project ID numbers. This implies that if a predecessor task is inserted or
deleted the ID number will increase or decreases causing the incorrect tasks
to be linked.

If this is true (which we have so far found to be so) is there a work around?
 
M

Mike Glen

Hi Rose,

Welcome to this Microsoft Project newsgroup :)

The ID numbers are adjusted to be consecutive and the linked IDs will change
to maintain the original logic. Make sure in Tools/Options.../Schedule tab
that the Autolink inserted or moved tasks is UNCHECKED.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
B

Brian K - Project MVP

RoseC said:
When linking tasks beween projects it appears that the links are
between project ID numbers. This implies that if a predecessor task
is inserted or deleted the ID number will increase or decreases
causing the incorrect tasks to be linked.

If this is true (which we have so far found to be so) is there a work
around?

I was pretty sure this was wrong but I tested it again just now and
inserting a task into the project before the sucessor in a
cross-project link does not break the link. Adding new tasks or moving
the linked task does not cause the wrong task to be linked.
 