Hi,
I have the following question, lets say I have a new project namely:
1) Project_Name
2) Summary1
3) Task1
4) Task2
5) Task3
6) Summary2
7) Task1
8) Task2
9) Summary3
10) Task1
If I want all the work on Summary1 & Summary2 to start at the same time
should the proper way of linking these items be by linking Summary1 &
Summary2 with (SS) type linkage? Is that a proper way of doing that linkage?
Also, I would like Task2 in Summary2 to be linked to the next process
either( Summary3 or Task1 of Summary3)? Is this correct linkage? Becuase if
I link (8) and (9) would that mean that all the tasks in item (9) be done
only after item (8) if I have a (FS) link?
The bottom question is: Are the links I'm asking for your review
appropriate in PM?
-jaime
I have the following question, lets say I have a new project namely:
1) Project_Name
2) Summary1
3) Task1
4) Task2
5) Task3
6) Summary2
7) Task1
8) Task2
9) Summary3
10) Task1
If I want all the work on Summary1 & Summary2 to start at the same time
should the proper way of linking these items be by linking Summary1 &
Summary2 with (SS) type linkage? Is that a proper way of doing that linkage?
Also, I would like Task2 in Summary2 to be linked to the next process
either( Summary3 or Task1 of Summary3)? Is this correct linkage? Becuase if
I link (8) and (9) would that mean that all the tasks in item (9) be done
only after item (8) if I have a (FS) link?
The bottom question is: Are the links I'm asking for your review
appropriate in PM?