J
James
I'm using EPM 2003 and am looking for a way to produce a report that would
list tasks grouped by resource that have actuals in a defined period such as
the previous 2 weeks. Is there a way of getting this info in MS Project 2003
or through EPM?
Thanks,
James
list tasks grouped by resource that have actuals in a defined period such as
the previous 2 weeks. Is there a way of getting this info in MS Project 2003
or through EPM?
Thanks,
James