Torben Andresen
Hi all.
I need to specify the physical location of where a task is to be performed
and then have Project re-schedule so that the same resource is not performing
multiple tasks at different locations. So even if the resources assignment
units is only 20% on to tasks they shouldn't be allowed to be scheduled at
the same time due to the fact that they're in to different locations. Is this
possible in Project?
Thanks in advance,
I need to specify the physical location of where a task is to be performed
and then have Project re-schedule so that the same resource is not performing
multiple tasks at different locations. So even if the resources assignment
units is only 20% on to tasks they shouldn't be allowed to be scheduled at
the same time due to the fact that they're in to different locations. Is this
possible in Project?
Thanks in advance,