R
Reider
I need to 'scrub' my project schedule for a customer submission, so that it
no longer shows any resources or Work hours for the project. I do still need
to show the Start / Finish Dates, % complete, and duration columns. I have
tried to set all tasks to Fixed Duration and remove the Effort Driven flag,
but still get date shifts on my Finish Date caused by the duration changing
when the resources are removed. Is there a way to lock down the duration and
dates, so I don't have to review each task one by one after I scrub the
schedule?
no longer shows any resources or Work hours for the project. I do still need
to show the Start / Finish Dates, % complete, and duration columns. I have
tried to set all tasks to Fixed Duration and remove the Effort Driven flag,
but still get date shifts on my Finish Date caused by the duration changing
when the resources are removed. Is there a way to lock down the duration and
dates, so I don't have to review each task one by one after I scrub the
schedule?