I have a tape out milestone date which I cant delay
therefore
I would like that it will not be possible to
make extention for a task that coming before the tape out
if its making a delay
You could set a "Finish No Later Than" constraint on your milestone.
Double click on the task and go to the advanced tab. Select the
constraint from the drop-down and set your date.