I would like to lock the last task - tape out
so it will not be able
to update tasks that want to finish after it start
 
D

davegb

I would like to lock the last task - tape out
so it will not be able
to update tasks that want to finish after it start

Not sure what you mean by "lock". Or the rest of your description.
Please elaborate so we can help you.
 
J

jony

Hi

I have a tape out milestone date which I cant delay
therefore
I would like that it will not be possible to
make extention for a task that coming before the tape out
if its making a delay

so I want to "lock" the tape out milestone
 
J

JulieS

Hi jony,

You could set a "Finish No Later Than" constraint on your milestone.
Double click on the task and go to the advanced tab. Select the
constraint from the drop-down and set your date.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top