Logic through re-scheduled tasks.

P

Philg

I have a schedule that has been baselined; when I re-schedule, the links I
have creating still remain attached to the baseline, how can I show the links
flowing through the re-scheduled dates rather than through the baselines.
Is this possible ?
Thanks in advance
Phil
 
J

John

Philg said:
I have a schedule that has been baselined; when I re-schedule, the links I
have creating still remain attached to the baseline, how can I show the links
flowing through the re-scheduled dates rather than through the baselines.
Is this possible ?
Thanks in advance
Phil

Philg,
First of all, links are never attached to baseline values. Baseline
values are nothing more than a snapshot of select Project data fields
stored in spare fields. They are not part of Project's active scheduling
engine. Task links (predecessors and successors) are attached to the
schedule Start and Finish fields. I suspect you may not have
calculation, (Tools/Options/Calculation tab), set for automatic so it
may not appear that the links are moving as the Start and Finish fields
move in response to the dynamics of the schedule.

John
Project MVP
 