R
RTucker
Hello all,
We had a VBA curruption issue that was resolved only by inserting the bad
file into a new blank file at Task line 1, then disabling the link to the bad
file. (everyone follow that?) An export/import of XML would not work,
either from possible bad logic in the XML file, or due to the XML filesize of
350MB. Even a four processor, 3GB RAM PC would not import the XML file.
Anyway...
After disabling the external link I was left with a new project file with
all my original data. I am left with the question of how does Project track
the baseline values on tasks and for the project overall.
Understandably, the date the last Baseline was performed no longer appears
in parenthesis, in Tools-Tracking. So, what do I do?
By baselining all tasks, I will lose all my variance, yes? I do not want to
rebaseline the entire project. I'm on a government project and the auditors
will not like that.
I rebaselined one task where the S/F dates matched the baseline dates, and
the (last baselined on) date is now showing. But does this validate all the
other baseline values for all the other tasks?
Project allows you to manually enter/edit baseline date values into task
records. What's up with that?!! Does MS Project track the baseline status
of each task, or only at the project level. I've reviewed the E/R diagram
from the Resource Kit, but don't see the answer.
Oh, one more, please...
In reviewing the baseline dates, I found a Milestone task with BLstart of
4/20/05 and a BLfinish of 4/16/05! How can that be?
We had a VBA curruption issue that was resolved only by inserting the bad
file into a new blank file at Task line 1, then disabling the link to the bad
file. (everyone follow that?) An export/import of XML would not work,
either from possible bad logic in the XML file, or due to the XML filesize of
350MB. Even a four processor, 3GB RAM PC would not import the XML file.
Anyway...
After disabling the external link I was left with a new project file with
all my original data. I am left with the question of how does Project track
the baseline values on tasks and for the project overall.
Understandably, the date the last Baseline was performed no longer appears
in parenthesis, in Tools-Tracking. So, what do I do?
By baselining all tasks, I will lose all my variance, yes? I do not want to
rebaseline the entire project. I'm on a government project and the auditors
will not like that.
I rebaselined one task where the S/F dates matched the baseline dates, and
the (last baselined on) date is now showing. But does this validate all the
other baseline values for all the other tasks?
Project allows you to manually enter/edit baseline date values into task
records. What's up with that?!! Does MS Project track the baseline status
of each task, or only at the project level. I've reviewed the E/R diagram
from the Resource Kit, but don't see the answer.
Oh, one more, please...
In reviewing the baseline dates, I found a Milestone task with BLstart of
4/20/05 and a BLfinish of 4/16/05! How can that be?