I have a project set up and all the resources assigned. How do I get project
to show me the crew size for each week of work?
Thanks,
(e-mail address removed)
 
M

Mike Glen

Hi Bob,

Welcome to this Microsoft Project newsgroup :)

Try the Resource Usage view.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen