Float/Slack Time

B

Bob Vardell

I have tasks set up and they are linked, in order, and then finally linked to
the milestone.
How do I have project show me the float time that I have before the task(s)
miss the milestones?
Thanks,
(e-mail address removed)
 
M

Mike Glen

Hi Bob,

Welcome to this Microsoft Project newsgroup :)

Try View/Table/Schedule to see the slack data.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
S

Steve House [Project MVP]

If your project is set up exactly as you've described it there's zero slack
or float in any of the tasks. You need to also have a deadline set for the
finish milestone (Task Information form, Advanced tab). Then Mike's
suggestion of the Schedule table will show you the slack.
 