Is there a way to mark a milestone as complete in PWA? If not, how do I mark
it complete in Project?
 
D

Dale Howard [MVP]

Leslie --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is devoted to
the Microsoft Project desktop application only. To answer your question,
no, you cannot mark milestones complete in PWA. Instead, use Microsoft
Project for this purpose. Double-click the name of the milestone task and
set the Percent Complete value to 100%. Hope this helps.
 
W

Wiley

Not in PWA. In Project you can do it in the Task From View or insert the
$Complete column. You cannot do it in the %Work Complete field.
 