R
RCR
I've seen several threads on this topic, but haven't seen the particular
problem that I am seeing with my install of Project 2000.
When I enter a *new* task, then enter WORK as my estimate (allowing project
to calculate DURATION), and then assign a resource (set at 80% MAX UNITS),
Project doesn't do what I want.
For example:
I enter Task1. I enter 2d WORK (duration stays at the default 1d?). Then I
select my resource (set at 80% MAX).
Project will then automatically set the resource at 200% to accomodate the
2d WORK and 1d DURATION that is there...
If I enter 1d WORK w/ the default 1d? DURATION, and then select a resource,
Proejct sets the UNITS to 100%
If I enter .5d WORK w/ the default 1d? duration, and then select a resource,
Project sets the UNTIS to 50%.
I don't understand why project is doing this with fixed unit, effort driven
tasks--udjusting UNITS--instead of adjusting the DURATION (based on the UNITS
and WORK entered).
Now, if I go back and "reselect" my resource, I get the desired resullt. 80%
MAX with a slightly extended DURATION based on the WORK (1d of WORK = 1.25d
DURATION)...but, I can hardly advise all of my PMs to make sure to select the
resource twice...
Any advice on this irksome issue?
RCR
problem that I am seeing with my install of Project 2000.
When I enter a *new* task, then enter WORK as my estimate (allowing project
to calculate DURATION), and then assign a resource (set at 80% MAX UNITS),
Project doesn't do what I want.
For example:
I enter Task1. I enter 2d WORK (duration stays at the default 1d?). Then I
select my resource (set at 80% MAX).
Project will then automatically set the resource at 200% to accomodate the
2d WORK and 1d DURATION that is there...
If I enter 1d WORK w/ the default 1d? DURATION, and then select a resource,
Proejct sets the UNITS to 100%
If I enter .5d WORK w/ the default 1d? duration, and then select a resource,
Project sets the UNTIS to 50%.
I don't understand why project is doing this with fixed unit, effort driven
tasks--udjusting UNITS--instead of adjusting the DURATION (based on the UNITS
and WORK entered).
Now, if I go back and "reselect" my resource, I get the desired resullt. 80%
MAX with a slightly extended DURATION based on the WORK (1d of WORK = 1.25d
DURATION)...but, I can hardly advise all of my PMs to make sure to select the
resource twice...
Any advice on this irksome issue?
RCR