microsoft project 2000 custom critical path

B

BBoler

I know that MS Project 2000 will either calculate one critical path or
calculate all of the critical paths. I want to create three differeent
critical paths based on three specific milestones all in one project
schedule. Is this possible?
 
J

Jim Spiller

Go to Tools-Options-Calculations and select "Calculate Multiple Critical
Paths". It will then calculate a critical path to each end point in your
project.
 
B

BBoler

I have taken this discussion to the Development Discussion Board becuase I
think my problem may require VBA. The problem is that I don't want the CP
calculated for EVERY endpoint in my schedule, only three specific ones.
 