C
Chris waller
Several colleagues and I use Project 2000 during our working day. We have
noticed that there appears to be an intermittent fault. That is some days you
can make changes to dates etc and days later you can go back to the same
project and it hasn't retained the changes. I thought at first it was a
problem with me not saving the work, but I have had a colleague sat and
watched what I have done and they have witnessed me saving the file only to
have the changes disappear. I have since learned that people in other areas
at work are experiencing the same kind of problem. Is anyone at Microsoft
aware of the problem and is there a fix or is it a glitch with our own
system? Was the install corrupted or do we need to change some settings in
order that this will work correctly again? As I am new to Microsoft Project I
do not know if it was set up correctly when it was installed or whether we
have to change some of the defaults so that it works in a way that is
compatible with the way we work. I would be grateful for views on the matter.
noticed that there appears to be an intermittent fault. That is some days you
can make changes to dates etc and days later you can go back to the same
project and it hasn't retained the changes. I thought at first it was a
problem with me not saving the work, but I have had a colleague sat and
watched what I have done and they have witnessed me saving the file only to
have the changes disappear. I have since learned that people in other areas
at work are experiencing the same kind of problem. Is anyone at Microsoft
aware of the problem and is there a fix or is it a glitch with our own
system? Was the install corrupted or do we need to change some settings in
order that this will work correctly again? As I am new to Microsoft Project I
do not know if it was set up correctly when it was installed or whether we
have to change some of the defaults so that it works in a way that is
compatible with the way we work. I would be grateful for views on the matter.