Microsoft Project 2003

M

Mkemm

I would like to know if there is a way to have a task start after another
task but FINISH one day before a different task. This way the number of days
the task would take would change.
 
M

Mike Glen

Hi Mkemm ,

Welcome to this Microsoft Project newsgroup :)

You could try using a hammock task with suitable lag or lead. Please see
FAQ Item: 19. Hammock Tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 