Dorothy721
Hi there:
Specifically, I would like to set up a view where I can take overallocated
resource's tasks and move them to underallocated resources. I can not figure
out an easy and simple way to compare resources tasks in order to do this.
For example, lets say I have a team member named Nate and one named Adam.
Nate and Adam can do the same tasks and work the same hours. Nate was
overallocated and therefore Adam has been recently assigned to the project.
How can I reallocate tasks EASILY? In resource usage view, it is difficult
to compare the individual hours breakdown for resources side by side in a
manner making them easy to move from one resource to another.
Specifically, I would like to set up a view where I can take overallocated
resource's tasks and move them to underallocated resources. I can not figure
out an easy and simple way to compare resources tasks in order to do this.
For example, lets say I have a team member named Nate and one named Adam.
Nate and Adam can do the same tasks and work the same hours. Nate was
overallocated and therefore Adam has been recently assigned to the project.
How can I reallocate tasks EASILY? In resource usage view, it is difficult
to compare the individual hours breakdown for resources side by side in a
manner making them easy to move from one resource to another.