C
crook
Is "Lag Time" or a "Start No Earlier Than" date the best way to
constrain a mid-project schedule delay?
This is a question I fielded from one of the PMs at my company earlier
today. This PM asks this question because he's had a project begin,
then be placed on hold.
Thanks!
Crook
constrain a mid-project schedule delay?
This is a question I fielded from one of the PMs at my company earlier
today. This PM asks this question because he's had a project begin,
then be placed on hold.
Thanks!
Crook