Mike Glen - a question

K

Karen

I read through your Microsoft Project 13.On the fourth page it talks about
Resource Cost which I can not find in Project which I assume this is in
relation to the figure (Gantt chart/split screen) showing Cost, Baseline
Cost, Act. Cost and Rem. Cost columns. How do I get to that point showing
these four additional columns?
 
M

Mike Glen

Hi Karen,

Welcome to this Microsoft Project newsgroup :)

Sorry, I've made a slight boob! From the Gantt Chart view, right click in
the Gantt Chart and select Split (or Window/Split), Now Right Click (not
double click) in the lower pane and select Resource Cost.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
K

Karen

thank you

Mike Glen said:
Hi Karen,

Welcome to this Microsoft Project newsgroup :)

Sorry, I've made a slight boob! From the Gantt Chart view, right click in
the Gantt Chart and select Split (or Window/Split), Now Right Click (not
double click) in the lower pane and select Resource Cost.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 