I am printing a milestone report to show significant tasks for my project.

When I print my report I get the milestones, but I also get their Summary
tasks printed on the report.

Is there any way that I can just get the actual milestone task (0 days ones)
printed on my report and not the Summary tasks??

Thanks in advance

Susie
 
R

Rod Gill

The report is probably using the Milestones Task Filter which is probably
set to show summary rows as well. To turn this off:
Select Project, Filtered For, More Filters
Select the Milestones filter then Click Edit.
Deselect the Show Summary Rows Option
Click OK then Close and try your report again.
 
S

Susie

Hi Rod,

Thanks for your help.

This still doesn't solve my reporting problem though, I still see summary
tasks in my Milestone report.

Any more ideas?
 
T

texasroy

Susie:
Go to "View" "Reports", "Custom". Choose "Milestones" and "Edit". Uncheck
the summary lines. This should do it for you.

Roy
 
M

Mike Glen

Hi Susie,

Welcome to this Microsoft Project newsgroup :)

Try Tools/Options.../View tab and remove the tick in Show summary tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top