Joe said:
I have several milestones with durations on them. I wonder if there is a way
to have them display on the gant chart for the end-date rather than at the
start date?
Joe,
Yes there is but in my opinion milestones NEVER have duration. They
should only be used to mark the completion of a task or series of tasks.
A milestone marks a point in time.
Nonetheless if you really want to pollute your plan, go to Format/Bar
Styles and change the "from" and "to" column of the bar style definition
for milestones to be "finish" instead of "start".
Sorry, I guess I got a bit carried away.
John
Project MVP