If Resource A has been allocated to Tasks 1, 2, 3, 4 and 5 - the BCWS values
for Tasks A, B and C are accurate, but those for D and E are $0.00? It's
similar with Resources B and C also.
The Standard Rate for all the resources was probably put at the same time -
after the project was baselined.
Does any one know if I can get the missing BCWS values or do I have to
calculate the values?
for Tasks A, B and C are accurate, but those for D and E are $0.00? It's
similar with Resources B and C also.
The Standard Rate for all the resources was probably put at the same time -
after the project was baselined.
Does any one know if I can get the missing BCWS values or do I have to
calculate the values?