S
Scott
I have tasks in my project that are missing cost (budget) data. Not all of my
tasks have missing cost data however.
I have rates and resources defined for all resources.
I have changed out resource namess for those tasks that do not have costs
defined with those task that do. Not a fix, so the resource definition does
not seem to be a problem. The problem seems to lie with the task itself.
I have also compared those tasks with and with out costs and found no
difference in settings. I'm stumped! I am simply trying to get budget
associated with each task and thought it was a simple as rate x duration!
Has any one else seen this problem and have a few tips?
Thank, Scott
tasks have missing cost data however.
I have rates and resources defined for all resources.
I have changed out resource namess for those tasks that do not have costs
defined with those task that do. Not a fix, so the resource definition does
not seem to be a problem. The problem seems to lie with the task itself.
I have also compared those tasks with and with out costs and found no
difference in settings. I'm stumped! I am simply trying to get budget
associated with each task and thought it was a simple as rate x duration!
Has any one else seen this problem and have a few tips?
Thank, Scott