I've started using the Work column to track work - however, I've now found
new problems.
1) For some reason the hours are not totaling up on the upper level tasks. I
have hours plugged in, but it is still showing '0' hours on all upper level
tasks above.
2) It seems that my predescessors are not functioning properly. Is there a
general "Do / Don't do" for using the linking function?