Hi Ken,
This post seems to be conflicting with the original post. Do you
want to take tasks which are incomplete that are in the past and
move them to start on the current date or take tasks that are
scheduled in the future and put them in the past? If it's the
second, Dave gave you the correct answer -- remove predecessors or
constraints which have placed the tasks in the future. A task
without predecessors or constraints should be scheduled for the
original start date of the project.
If you want to take tasks which are scheduled in the past that are
incomplete and move them to start on the current date then choose
Tools > Tracking > Update Project, Reschedule uncompleted tasks to
start on....
I hope this helps. Let us know how you get along.
Julie
Project MVP