Teeder said:
The files are physically being moved regardless of where they are being
dragged to (we use our right button to drag and drop and choose move to avoid
the defaults), or they are being renamed in the same folder in windows.
Unfortunately this is hard to avoid in our case as there are about 150
projects on the go at any given time under approx.70 managers. Sometimes the
name has to change for the company it was created for has changed, and
keeping all of those projects in the same folder is possible but not the best
situation as each manager and team has their own fileing habits and
preferences. So to recap, there is definately only one file on the system for
each project, but the move causes that duplicate problem every time. Any
ideas Oh Great One.......and Master of all Court Jesters?
Teeder
Teeder,
I don't understand how a live working project file would change because
the company it was created for changed. It would be very rare indeed
that a company changes its name. It sounds to me like you are are
perhaps re-using a file for a new project for a different company. In
that case I suggest you use a template (not connect to the resource
pool) and then re-connect the new file to the resource pool each time it
is updated for "live" file use with a new company. Don't try to leave it
connected to the pool.
It also sounds like you need some company groundrules for using Project.
I am well aware that many manager like to "use their own process", but
if that is not consistent with good Project file management, then a set
of rules is required. There are many things you can do with Project that
are not recommended, (e.g. linking summary lines, "backward pass"
linking, resources assigned to summary lines etc.), and without a set of
groundrules, users tend to do what "looks good".
Other than the above, I don't have any magic solutions for the file
structure you are trying to use.
John
Project MVP