M
Mr. T
I have undoubtedly made a system level change, but can't for the life of me
figure out what.
On both new and existing projects, when I link two tasks together using
standard Finish to Start relationships, then modify the duration of the
earlier tasks, the down stream task will not update. Example: Task A has 2
days duration, immediately followed and linked to task B. When I extend the
duration on task A to 4 days in length, I expect task B to start 2 days
later. Graphically, I can see the links in the Gantt chart, however the
downstream task start date remains unaffected.
figure out what.
On both new and existing projects, when I link two tasks together using
standard Finish to Start relationships, then modify the duration of the
earlier tasks, the down stream task will not update. Example: Task A has 2
days duration, immediately followed and linked to task B. When I extend the
duration on task A to 4 days in length, I expect task B to start 2 days
later. Graphically, I can see the links in the Gantt chart, however the
downstream task start date remains unaffected.