MS Project 2000 links not working

M

Mr. T

I have undoubtedly made a system level change, but can't for the life of me
figure out what.
On both new and existing projects, when I link two tasks together using
standard Finish to Start relationships, then modify the duration of the
earlier tasks, the down stream task will not update. Example: Task A has 2
days duration, immediately followed and linked to task B. When I extend the
duration on task A to 4 days in length, I expect task B to start 2 days
later. Graphically, I can see the links in the Gantt chart, however the
downstream task start date remains unaffected.
 
J

Jan De Messemaeker

Tools, Options, Calculation, set to automatic
If that doesn't help:
Is it only in this file? If yes, there is a circular relationship. Delete
all links from and to summary tasks.
Is it inly this or these tasks? You have entered an Actual Start

Hope this helps
 