MS Project 2002 - possible bug

L

Lauren K

Has anyone else using Professional 2002 found their
predecessors no long impacting task start dates? Any
ideas? I've looked at all typical culprits..
 
M

Mark Durrenberger

Check to see if you have entered any actuals on tasks that won't move. Also
of course, look for constraints like "must start on" and "must finish on"

Regards,
Mark


--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________

The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.

- Sir John Harvey-Jones
 
G

Guest

already checked those - no actuals, set up to start as
soon as possible... it just started happening to ALL my
plans (20+) and even new plans. Can't figure it out..
 
J

JackD

If you have a link to a summary task containing that task then the
dependency between the task which is the predecessor of the summary task and
the tasks under that summary task is hidden. If you have any dependencies
going to summary tasks that is the first place I would look.
You need to look very carefully as the dependency is not visible. Let me
give an example

x is a predecessor to a summary task (we will call it "summary")
a, b, c are tasks under summary and have dependencies a->b->c
x is planned to complete on Sept 1, 2005

If there is no work done on a, b or c then summary starts on sept 2 and "a"
starts on sept 2, followed by b and then c.

However, if there is an actual start on "a" in say July, then "summary"
starts in July. The question is where does "b" start? Well, even though it
only has a dependency on "a", it will not start until Sept 2. If you try to
move it earlier it will spring right back. This may not be what you are
expecting, but since x doesn't finish until then, any of the unstarted tasks
under the summary won't start before x is finished.

Finally (and it should be the first suggestion) go to tools menu / options /
calculation tab and make sure that calculation is set to automatic (or press
F9).

I'd also insert the "actual start" column and make sure that it is clear. It
can have dates even if there is no actual work on the task. That will pin
them in place.

-Jack
 
G

Guest

Thank you! Looks like the auto-calc was changed - I
completely forgot about that option. Thanks for the help!
 