JulieS said:
Hi Dan,
My answers are embedded.
--
I hope this helps. Let us know how you get along.
Julie
Visit
http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
DCook said:
I've been developing a quite large schedule and have never [knowingly]
baselined it but as I was analyzing all of the views, I noticed that
some of
them appear to have baseline characteristics in the Gantt chart. Is
there a
way I could have accidentally baselined only to show in certain views?
[Julie] No, if you have baselined a task, the data shows in all views.
Try adding the baseline start or baseline finish to the table (left)
side. I'm not sure exactly what you mean by "baseline characteristics"
but if there is data in the baseline field, the task has either been
baselined or data has been directly entered into one of the baseline
fields.
More
importantly, is there a way to completely remove the baseline? I only
want
to show what has been entered, we're not ready to baseline! Please
help!
[Julie] Sure, thing. Tools > Tracking, Clear baseline.
Hi, Julie - thanks for the quick response. I've checked the Baseline Start
and Finish columns and about 6 or 7 entries somehow had baseline dates (I
didn't enter them specifically there - never had those columns showing). I
labeled them as "NA" just like all the other entries and in this particular
view I was in at the time, it cleared the baseline "characteristics" from the
Gantt (baseline progress bars, etc.).
Now, when I check in other views, the Gantt shows many tasks as having
baseline progress bars. But, when I view Baseline Start and Finish 1, 2, and
3 (didn't feel it was necessary to go through all 10 before asking for help),
the columns all read "NA." Could this have anything to do with the
customized tables I've created? I'm really not sure how any baseline
information got into this schedule in the first place. I'm tempted to start
over completely but that's a last resort because there are so many uniquely
defined attributes to the project file.
Oh, I didn try Tools > Tracking, Clear baseline but it doesn't seem to have
any effect. Do you have any more suggestions?
Regards,
Dan