MS Project 2003 Server No Outlook Email on Publish

M

MGMartinez

Hello,

Has anyone experienced a sudden disconnect between MS Project 2003 Server
and Outlook when in Project and a new, updated or deleted task suddenly does
not generate an email to the assigned resource(s) on collaborate/publish?

I verified my Project Web Access (PWA) email notification setup and nothing
has changed from when it was working correctly. Verified that I was still
the owner of the schedule.

Any help on this issue would be greatly appreciated.
 
M

Mike Glen

Hi MGMartinez,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
M

MGMartinez

Thank you - I found that a new firewall rule was put into effect, which
restricted project server emails. However, I will visit those sites for
future issues.
 