I did a small Earned Value test which had 5 tasks (+ summary row)
Columns:
BAC, AC, %, EV, PV, CV, SV, EAC and I used physical % complete to
calculate ev.
Anyways, MSP calculates those columns right and I get the data what I
need, but when I try to create visual report it shows only zeros in
the report? I tested the default eva report which was included with
MSP and I did try to make new one, still only zeros. What I'm missing?