M
Muks
I have a situation which I would like to capture in my schedule.
Planned Start Date : 02/16/2005
Planned Finish Date : 02/18/2005
Planned Work : 24 hrs
Actual Start Date : 02/16/2005
Actual Finish Date : 02/21/2005 (resource has not worked on the task in
between)
Actual Work : 24 hrs
When I am trying feed in data, system is changing effort to 32 hrs. I would
like system to change "Unit" not "Duration/Effort". I tried with "Fixed
Duration" as well as "Fixed Work" Type.
Appreciate suggestions.
Planned Start Date : 02/16/2005
Planned Finish Date : 02/18/2005
Planned Work : 24 hrs
Actual Start Date : 02/16/2005
Actual Finish Date : 02/21/2005 (resource has not worked on the task in
between)
Actual Work : 24 hrs
When I am trying feed in data, system is changing effort to 32 hrs. I would
like system to change "Unit" not "Duration/Effort". I tried with "Fixed
Duration" as well as "Fixed Work" Type.
Appreciate suggestions.