H
Hugh
I have a 14,000 line consolidated project file that is made up of 8
subplans with interdepencies between them. Many unusual things have
started happening to my project plan including basic things like
Summary task dates not calculating correctly (see below example).
My question is the following: Is there a limit that MS Project has
where it no longer functions correctly such as number of tasks or
filesize, etc?
Summary 1 day Fri 5/11/07 Mon 5/14/07
x 1 day Mon 8/21/06 Tue 8/22/06
x 1 day Mon 8/21/06 Tue 8/22/06
x 1 day Mon 8/21/06 Tue 8/22/06
x 1 day Mon 8/21/06 Tue 8/22/06
I'm using MS Project Professional 2003.
subplans with interdepencies between them. Many unusual things have
started happening to my project plan including basic things like
Summary task dates not calculating correctly (see below example).
My question is the following: Is there a limit that MS Project has
where it no longer functions correctly such as number of tasks or
filesize, etc?
Summary 1 day Fri 5/11/07 Mon 5/14/07
x 1 day Mon 8/21/06 Tue 8/22/06
x 1 day Mon 8/21/06 Tue 8/22/06
x 1 day Mon 8/21/06 Tue 8/22/06
x 1 day Mon 8/21/06 Tue 8/22/06
I'm using MS Project Professional 2003.