Physical Complete is a purely subjective indicator and there's no
mathmatical rule to govern its rollup. Thus what you're asking just isn't
possible in Project. You'll need to manually enter completion estimates for
the summaries. You might want to rethink the use of physical % complete
anyway as it's an incredibly unreliable indicator of progress - generally
when you look at progress you're interested in "are we on track with the
schedule?" and "are we on budget?" Physical % Complete doesn't tell you
anything about either one and for most types of projects is impossible to
estimate with any reliability at all. If you're painting a wall and have
half of it done, then it's pretty straight forward to say it's 50% physical
complete. But suppose you were designing an engine ... just what would
saying it's "50% physical complete" mean? Half the drawings? Half the
systems? The front done but still working on the back?
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Derek@Kendal said:
How do I get MS Project 2003 to show the Summary physical % complete ?
I've
entered individual task %'s but it does not bring them up to the Summary
task.