John Horton
When I import a 2003 file into 2007 I am having all kinds of weird problems
with the assignment dates and then as a result task durations. It seems that
when a 2003 file is opened by 2007 all work is re-amortized across time. I
think what is happening is that the work is re-contoured!?!? As a result
durations and assignments are all goofy but start dates, work, remaining
work, all seem totally unchanged.
We build all of our files with generic resources and then replace the hours
as we go with the actual resource. What has happened is that we have zeroed
out a days work for the generic so we can give the hours to the actual, when
opened in 07 the assignment has remaining hours reassigned back to the start
of the task. The total hours and remaining hours still balance but durations
and assignments are all over the place.
Ideas? I need to convert dozens of projects from 2003 to 2007 but they all
have assignments at that have been modified.
with the assignment dates and then as a result task durations. It seems that
when a 2003 file is opened by 2007 all work is re-amortized across time. I
think what is happening is that the work is re-contoured!?!? As a result
durations and assignments are all goofy but start dates, work, remaining
work, all seem totally unchanged.
We build all of our files with generic resources and then replace the hours
as we go with the actual resource. What has happened is that we have zeroed
out a days work for the generic so we can give the hours to the actual, when
opened in 07 the assignment has remaining hours reassigned back to the start
of the task. The total hours and remaining hours still balance but durations
and assignments are all over the place.
Ideas? I need to convert dozens of projects from 2003 to 2007 but they all
have assignments at that have been modified.