A
Alan Smith
I've searched a number of entries in different forums to solve my problem but
have been unsuccessful.
I have allocated a resource to a task that has a duration of 14 days. I then
set the calendar for that resource as having 5 days vacation in the middle of
that duration. The problem is that the schedule has not taken any notice of
the vacation and has still assumed the resource is working during that period.
I would appreciate some assistance in solving this problem.
My email address is (e-mail address removed)
have been unsuccessful.
I have allocated a resource to a task that has a duration of 14 days. I then
set the calendar for that resource as having 5 days vacation in the middle of
that duration. The problem is that the schedule has not taken any notice of
the vacation and has still assumed the resource is working during that period.
I would appreciate some assistance in solving this problem.
My email address is (e-mail address removed)