Hi..
Its possible..
If you now give the duration automatic in hours then that means in your
standard settings the durationstarndsrt in hour.
So make the the standart entry for the duration as day. Noe if you enter
the duration it will be automatic day for all tasks..If you give the duration
for subtasks hour (MANUAL for examle task1: 16 h) then you will have the
duration of substaks hor and the duration of summaray task in day..
I hope this helps.
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.