Multiple SPI for Multiple Baselines

B

Brian Lukanic

I want to create a custom field with a formula that calculates SPI against a
non-default baseline (I realize that you can go into Options to change which
baseline the EV fields calculate against). Let's say I have 8 baselines
saved: Then I would like 8 SPI columns, each calculating against a different
baseline.

I don't know the correct syntax in the formula window when I add a text
column. I am assuing I need to use DateDiff, and of course SPI is EV/PV. Can
someone help me with the code that I would need to use in the formula box?
 