Hi All,

I have created filters for different task individually (Ex: task to be
completed in next 4 weeks for A, Task to be completed in next 4 weeks
and so on).
I would like to know if any filter or macro ( or any other way) is
possible by which i can use on filter instead of so many? It should
first ask me to choose a task and filter it.
All the filters will have the following common:

% completed <100%
finish <= "finish by:"?

I am working Ms Project 2007.

Thanks in advance,
SAM
 
J

Jan De Messemaeker

Hi,

Sorry Sam, but I do not understand.
Filters will only show you the taks that answer the conditions.
How can you filter "for one task"?

Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads

Need some PWA help 0
Weigh tasks 0
Resource graph/total for a filtered set of tasks 0
Request Form - Alert Team Member 0
Saving auto filters 5
Linking Tasks 3
Organising Tables. 3
Heading in reports 2

Top