Steve Scott
Hi, I have several thousand tasks that need to be updated and for each one I
need to do the following: Assign Person A at 50% effort to the task and
Person B at 50% so they are essentially doing half the work each. However,
when I try this on the following example I do not get the results I need.
Task is 19 days in duration but only has 2 hrs of work to be carried out
sometime in the 19 days. Task Type is Fixed units, Effort Driven. When I
open up the Resource Information dialog box and add in the two resources at
50 units each, the assigment at 50% effort is shown correctly in the Resource
names field; the work remains at 1hr, but the duration is shortened to 0.13
days (based on 8hr day) and the finish date comes in earlier accordingly.
How do I get to the results I need (ie the duration doesnt change) bearing in
mind I have several thousand tasks to update. I have tried changing the task
type to fixed duration and this does not help with my approach either.
need to do the following: Assign Person A at 50% effort to the task and
Person B at 50% so they are essentially doing half the work each. However,
when I try this on the following example I do not get the results I need.
Task is 19 days in duration but only has 2 hrs of work to be carried out
sometime in the 19 days. Task Type is Fixed units, Effort Driven. When I
open up the Resource Information dialog box and add in the two resources at
50 units each, the assigment at 50% effort is shown correctly in the Resource
names field; the work remains at 1hr, but the duration is shortened to 0.13
days (based on 8hr day) and the finish date comes in earlier accordingly.
How do I get to the results I need (ie the duration doesnt change) bearing in
mind I have several thousand tasks to update. I have tried changing the task
type to fixed duration and this does not help with my approach either.