Newbie Question - How to delay a project

D

Damien Sawyer

Hi,

I have a project that was put on hold for a few weeks. Can someone
please tell me the 'proper' way to include this delay so that the
scheduled dates move forward?

Thanks in advance,



Damien Sawyer
 
J

JulieS

Hi Damien,

Try Tools>Tracking>Update Project. Click the radio button next to
"Reschedule uncompleted work to start after: and enter the anticipate
"re-start" date. Click "Entire Project"
Click OK.

Hope this helps. Let us know how you get along.
Julie
 
R

Reid McTaggart

If work has not yet begun, you can simply change the project start date:
(Project, Project Information).

If work has been done, nad the remainder needs to be delayed, you can go to
Tools, Tracking, Update Project, Reschedule Uncompleted Work to Begin After:
[set date].

-Reid
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top